If a PV result is less than 80 percent, what will happen to the 3-M certification?

Study for the OPNAVINST 4790.1J Ship's Maintenance and Material Management Exam. Use flashcards, multiple choice questions, and comprehensive explanations to prepare effectively for your test!

In the context of the Ship’s Maintenance and Material Management (3-M) Manual, if a Performance Verification (PV) result is less than 80 percent, it indicates a significant deficiency in meeting the required standards for the 3-M certification. Such a low score signifies that the command is not effectively managing its maintenance and material processes. As a result, the protocol outlined in the manual stipulates that the certification will be revoked.

Revocation is a serious consequence that reflects the command's inability to uphold the standards necessary for continued certification in the 3-M system. The motivation behind this policy is to ensure that only commands demonstrating competence and effectiveness in maintenance management retain their certification. Revoking the certification serves not only as a corrective measure for the command but also as a means to safeguard the overall integrity and reliability of the 3-M program.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy