What does the 3MC need permission for regarding the force revision installation?

Study for the OPNAVINST 4790.1J Ship's Maintenance and Material Management Exam. Use flashcards, multiple choice questions, and comprehensive explanations to prepare effectively for your test!

In the context of the 3-M Manual, the 3MC (Maintenance Material Management Coordinator) is responsible for managing the scheduling and execution of maintenance tasks, including force revision installations. One of the critical responsibilities is overseeing the timeline of these installations to ensure mission readiness and compliance with maintenance schedules.

Delaying the installation would require explicit permission because it can impact the overall maintenance schedule and readiness of the ship. Such decisions must be carefully considered to avoid disrupting operational capabilities and must align with established priorities and timelines.

The other options, while related to management and resource allocation, do not require permission in the same direct manner as delaying an installation. For example, acquiring funding and changing installation teams may involve other stakeholders and escalations, but the need for explicit permission to delay directly involves the scheduling and availability of maintenance resources, making it a more immediate and consequential action.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy